 2018 Golf Course Construction Progress

Permitting Status Summary 

 

 

Jurisiction/ Permit

 

Status

 Permit Issuance

(Anticipated) 

(Town of Shelburne)

Parking Lot Modifications 

Parking Lot (Building) Permit 

 

Permit issued 

to be issued after 30 day appeal period

 

18-Apr

25-May

Golf Course Consolidation

Site Plan and Condition Use Approval

Course Const. Zoning(Building) Permit

N/A

Public Hearing Closed 

to be issued after 30 day appeal period 

N/A

16-May

15-Jun

Porch Addition

Porch Zoning (building) Permit 

Dev. Review Board Hearing 16-May

to be issued after 30 day appeal period 

6-Jun

6-Jul

(State Of Vermont)    

Construction Stormwater Permit

Issued  30-Apr

Operational Strmwater Permit 

Tech Review Complete, In Public Comment Period 1-Jun

Wetland Permit 

Awaiting State Site review 30-Jun
(Act 250)    

Land Use Permit

Hearing on May 10 2-Jul

Stream Corrider

Prelim Approval in Place, Awaiting final approval 10-May

Primary Agricultural Soils Impacts

Prelim Approval in Place, Awaiting final approval 9-May

Long Eared Bat Habitat Impacts 

Prelim Approval in Place, Awaiting final approval 10-May

Historic Preservtion 

Final Approval in Place  N/A

Archaeology 

Prelim Approval in Place, Awaiting final approval 10-May

Construction Stormwater Runoff 

Final Approval in Place 30-Apr

Post. Construction Runoff 

Tech. Approval, Awaiting  Public Comments  1-Jun

Wetland Permit 

Application Awaiting Site Review, Public Notice  30-Jun